G330国道雅湖至十八里立交段整治工程预计6月完工
2021-04-21 八咏建设 469
拼争交通项目 畅“动脉”促发展
G330国道雅湖至十八里立交段整治工程预计6月完工
Striving  to Smooth Development
The Improvment Project of Yahu- Shibali Interchange Section of G330 National Highway to be Completed in June



通讯员 方俊翔


Correspondent: Fang Junxiang

日前,在G330国道雅湖至十八里立交段整治工程施工现场,工人们合力抬起重达200公斤的路缘石,在道路一侧进行铺砌作业。项目经理吴继焕说:“整治工程预计今年6月完工,届时该路段将以双向六车道的崭新面貌出现在市民面前。”
A few days ago, at the construction site of the improvement project of Yahu to Shibali Interchange Section of G330 national highway, workers joined together to lift up 200 kg of curbs and pave on  side of the road. Wu Jihuan, the project manager, said: "the improvement project is expected to be completed in June this year. By that time, the road section will appear in front of the public with a new look of two-way six lane road."

G330国道是金华市“七纵七横”国省道网中的重要一横。作为G330国道整体扩容提升改造的重要组成部分,G330国道雅湖至十八里立交段整治工程起于雅湖村,终于十八里互通。此次整治的道路长约2.13公里,双向四车道将增加至双向六车道,整条道路将拓宽至40米,项目总投资达8010万元。
G330 national highway is one of the most important national and provincial highways in Jinhua.  As an important part of the overall expansion and upgrading of G330 national highway, the improvement project of Yahu to Shibali Interchange Section of G330 National Highway starts from Yahu village and ends at Shili interchange. The length of the improved road is about 2.13 km, the two-way four lane road will be upgraded to two-way six lane road, and the whole road will be widened to 40 meters, with a total investment of 80.1 million Yuan.

“目前已完成路基、桥梁下部和部分路段的沥青混凝土路面工程,下一步将在保证质量的前提下加快项目进度,完成剩余路基工程、梁板架设、沥青路面基层和面层、交安和绿化工程。”讲到施工进度,吴经理已经做好了每一步施工的计划安排。
"Now, the asphalt concrete pavement works of the subgrade, the sub structure of the bridge and some sections have been completed. The next step is to speed up the project progress on the premise of ensuring the quality, and complete the remaining subgrade works, beam and slab erection, asphalt pavement base and surface, traffic safety facility and landscape. "Speaking of the construction progress, manager Wu has made a good plan for each step of construction.


自2020年5月底本项目进场施工以来,项目部积极配合金东交投集团,与有关乡镇、部门及各管线单位对接沟通,抢时间,争进度,攻难关,加快推进政策处理和管线迁改工作。在集团公司和周边企业的大力支持下,努力克服沿线管线众多、施工作业面狭窄、涉路施工安全保障压力大等困难,目前累计完成产值5060万元,占合同价的63%。
Since the start of construction of the project at the end of May 2020, the project department has actively cooperated with Jindong Transportation Investment Group to communicate with relevant villages and towns, departments and pipeline company, so as to work ahead of  the time, strive for progress, overcome challenges, and accelerate policy processing and pipeline relocation. With the strong support of the Group Company and nearby enterprises, the company has made great efforts to overcome the difficulties of numerous pipelines along the line, narrow construction work site and high pressure of road related construction safety guarantee. At present, the accumulated output value is 50.6 million Yuan, accounting for 63% of the contract price.

“这条道路车流量很大,尤其是上下班高峰期经常会出现拥堵情况,希望道路整治项目早日完成。”说起G330国道金东区雅湖至十八里立交段的整治工程,周边村民非常期待。
"The traffic flow of this road is very large, especially in rush hours. We hope that the road improvement project will be completed as soon as possible. "Talking about the improvement project of Yahu to Shibali interchange in Jindong District of G330 national highway, the surrounding villagers are quite looking forward to it.